|
|
Use Estimates To Communicate Risk As
Well As Effort, Cost, and Schedule
Estimating is one of the most difficult and error prone tasks facing project managers.
Project managers are often required to develop estimates quickly with very incomplete
information. Since budgets, staffing, and even the strategic direction of a project are
driven by the estimating process, problems with estimates can have severe consequences.
When you have done your best with the information available, but the information available
is inadequate for a reliable estimate, communicate the risk inherent in the estimate.
Communicating risk with an estimate is a surprisingly easy, yet powerful, way to convey
significant valuable information to management. There are two ways to communicate risk
with an estimate:
- Include all key assumptions with the estimate.
- Present the estimate as a range -- pessimistic, most likely, and optimistic.
Key Assumptions
Bad estimates are often the result of the estimator making bad assumptions. Moreover, even
good estimates can be rendered obsolete if the underlying assumptions later prove to be
invalid. Key areas to consider include:
- What is being estimated (include list of deliverables).
- What is not being estimated.
- Resource requirements.
- Responsibilities with target dates.
- Environmental assumptions.
Risk will be related to two factors:
- Assumptions that have a high probability of not being valid.
- Assumptions that, if invalid, can cause significant estimating variances.
Present Estimate as a Range
Presenting estimates as a range also communicates risk. Mosaic recommends three estimates
-- optimistic, most likely, and pessimistic. (Note: Do not use the terms "worst
case" or "best case.") Consider the following effort estimates which
illustrates how communicating a range of estimates conveys significant additional
information.
Work Hour Estimate |
Comment |
10,000 work hours |
There is no way to judge the risks or
reliability of the estimate |
optimistic: 9,900 hours
most likely: 10,000 hours
pessimistic: 10,100 hours |
The estimator implies a precision that is not
possible. Therefore the estimate is not reliable. |
optimistic: 8,000 hours
most likely: 10,000 hours
pessimistic: 13,000 hours |
This may be a reasonable estimate of the
effort. |
optimistic: 8,000 hours
most likely: 10,000 hours
pessimistic: 50,000 hours |
The estimator implies such a wide range that
the factors behind the "pessimistic" estimate need to be explored before
proceeding. |
Each of these estimates has the same "most likely" estimate of effort, yet
each estimate conveys very different information about the risk associated with the
estimate.
Summary
Risk should always be communicated with an estimate. Risk information is important to
management and it can be easily communicated with an estimate.
Back to Risk Management Tips
For questions or comments please email
©2001 Mosaic, Inc.
|